Foundation work

This beautiful Saturday morning was used to post a little about the progress of the build.

We have set up a recording that takes like 3 pictures an hour during the day😄 hopefully we will get a 5 min film showing the diligent builders 😂

The delay tank for the rainwater almost ready (or as the installers say the cooling for the nuclear power plant😂😂😂)

The district heating almost finished, one weld to go. The oil separators in place, only electricity and fiber remain. On Monday, the excavation will begin, then the plinths for the steel frame will be cast.

A lot is happening now, to be continued.